Base Generation Charges
Energy you consume from the grid is billed directly using 3CE’s generation rates.
Manage your monthly energy costs and easily track your export credits for solar, wind, or on-site generation.
For customers enrolled in legacy NEM 1.0 or 2.0, 3CE handles your clean power generation and export credits, while your utility provider manages transmission and delivery.
For customers enrolled in legacy NEM 1.0 or 2.0, 3CE handles your clean power generation and export credits, while your utility provider manages transmission and delivery.
Energy you consume from the grid is billed directly using 3CE’s generation rates.
Exported surplus power earns CPUC-approved hourly credits that roll over to offset current or future charges.
Each December, your export adjustments balance out and any remaining credits automatically offset your 3CE charges.
It is how 3CE bills customers with on-site solar, wind, or energy generation systems, succeeding the legacy NEM 2.0 tariff.
"Net Billing Tariff" is the official CPUC name. 3CE calls it the "Solar Billing Plan" to match PG&E and SCE terminology.
Any new on-site generation system approved after April 15, 2023. Residential launched in June 2024; qualifying commercial/ag enrolls in 2026.
Energy used is billed at 3CE generation rates. Excess energy sent to the grid earns hourly export credits to offset your charges.
Compensation paid per kilowatt-hour (kWh) when you generate more energy than you use, based on hourly wholesale electricity rates.
CARE or FERA customers receive an extra $0.00396 per kWh on top of their export credits for nine years.
All 3CE generation services true-up every December. You will have a separate true-up with PG&E/SCE for delivery services.
At your December true-up, if your system generated more total energy than you consumed over the entire year.
It applies automatically as a bill credit. Residential customers with $200+ in surplus can request a check payout within 45 days.
Customers remain on NEM 1.0 for 20 years from their original approval date before automatically transitioning to the Solar Billing Plan.
Customers stay on NEM 2.0 for 20 years from approval. Moving from NEM 1.0 to 2.0 previously does not reset this timeline.
To promote energy affordability, increase grid reliability, and encourage the adoption of home battery storage systems.
Leaving early permanently moves you to the Solar Billing Plan. 3CE recommends comparing plans and consulting your solar installer.
Handled by PG&E or SCE. Minimum monthly utility delivery charges still apply.
Managed by 3CE. We track what you consume versus what you push back to the grid.
Each month, you are only billed for the net energy you consume beyond what you generate.
Our annual true-up statements arrive right on schedule every January or February, making tracking easy.
If you generate excess electricity over the course of your 12-month billing cycle, you will earn Net Surplus Compensation (NSC). Your payout is calculated by multiplying your excess kWh by 3CE’s NSC rate.
The bonus can automatically apply as a true-up bill credit, or you can request a direct check payment within 45 days of receiving your annual true-up statement.
Rates apply per kWh of total excess generation (Effective Dec 1, 2025).
$0.023/kWh
$0.010/kWh
You are on the SBP tariff if your solar system’s interconnection agreement was approved prior to April 15, 2023. Agreements approved after this date fall under the newer Solar Billing Plan.